Development Region | Central Development Region |
Zone | Sagarmatha |
District | Solukhumbu |
Intake Site | Chheskam |
Powerhouse Site | Bun and Gudel |
Latitude | 27 0 32'08"N-27 0 30'51"N |
Longitude | 86 0 51'23"E- 86 0 53'54"E |
Name of River | Hongu Khola |
Nearest Town | Salleri Bazaar |
Type of Scheme | Run-of-River |
Gross Head | 210.00 m |
Net rated Head | Net rated Head |
Installed Capacity | 22,000.00 kW |
Average Annual Energy after Outage | 137.89 GWh |
Catchment Area | 372 km 2 |
Mean Annual Discharge | 22.49 m 3 /s |
Design Discharge (Q42.85) | 13.00 m 3 /s |
Riparian Release | 0.555 m 3 /s |
Design Flood Discharge | 424.0 m 3 /s (100 years flood) |
Average Annual Precipitation | 1914.9 mm |
Type of Weir | Gravity free flow with spill way |
Length of Weir | 36.5 m |
Crest Elevation | Crest Elevation |
Crest Elevation | Sloping with free overflow |
Undersluice Opening (W X H) | 3.5 m x 3.0 m |
Undersluice Crest Level | 1594.4 masl |
Type of Intake | Side Intake with Orifice3 |
Nos of Opening | 3 |
Size of Intake (W x H) | 2.8 m x 2.5 m |
Size of Trash Passage (W x H) | 1.5 m x 1.5 m |
Intake Sill Level | 1597.80 m |
Length of Gravel Trap | 12 m |
Width of Gravel Trap (Avg.) | 10.4 m |
Overall depth | 5.5 m |
Particle size to be trapped | 2-200 mm |
Flushing Channel | L = 42 m, W = (1.2 m – 1.3 m), H = 1.2 m |
Type of Intake | Side Intake with Orifice3 |
Nos of Opening | 3 |
Size of Intake (W x H) | 2.8 m x 2.5 m |
Size of Trash Passage (W x H) | 1.5 m x 1.5 m |
Intake Sill Level | 1597.80 m |
Length of Gravel Trap | 12 m |
Width of Gravel Trap (Avg.) | 10.4 m |
Overall depth | 5.5 m |
Particle size to be trapped | 2-200 mm |
Flushing Channel | L = 42 m, W = (1.2 m – 1.3 m), H = 1.2 m |
Type | Surface , 4 bays |
Overall Dimension (L x B x H) | 55 m X 20.8 m X (4.0-6.8) m |
Inlet Transition Length | 16.4 m |
Particle Size to be settled | Greater than and upto 0.2 mm |
Trapping Efficiency | 98 % |
Type | Mild Steel |
Internal Diameter | 2.5 m |
Length | 157.00 m |
Steel Thickness | 10 mm |
Nos. of Anchor Blocks | 3 Nos. |
Type | Tunnel |
Finishing Diameter | 3.5 m x 3.8 (Inverted D-Shaped) |
Length | 3946.10 m |
Type | Circular, Underground Shaft |
Effective Depth | 33.5 m |
Diameter (Or size) | 8 m. |
Up Surge Level | 1610.93 masl |
Down Surge Level | 1588.96 masl |
Normal Operation Level | 1596.48 masl |
Type | Mild Steel Pipe |
Internal Diameter | 2.2 m |
Total Vertical Shaft Length | 127.5 m |
Steel Thickness | 14 mm to 18 mm |
Tunnel Enclosing Vertical Shaft | 3.2 x 3.2 m |
Type | Tunnel |
Finished Diameter | 3.5 m x 3.8 m (Inverted D-Shaped) |
Length | 481.71 m |
Type | Underground |
Size (L x W) | 40 m X 11 m |
Height (H) | 25 m |
Type | Tunnel |
Tailrace Length | 112 m |
Finished Size (W x D) | 3.5 m x 3.8 m (Inverted D- shape) |
Normal Tailrace Water Level | 1391.00 masl |
Type | Vertical Axis Francis Turbine |
Number | 3 (Three) |
Rated Output Capacity per unit | 7.85 MW |
Net Head | 202.061 m |
Discharge per Unit | 4.35 m 3 /s |
Efficiency | 90.0 % |
Type | Electronic Digital /Hydraulic |
Adjustment for Speed Drop | Between 0 to 5% |
Type | Vertical Axis Francis Turbine |
Number | Synchronous with Brushless excitation System |
Rated Output Capacity per unit | 8.9 MVA |
Power Factor | 0.85 |
Voltage | 11 kV |
Frequency | 50 Hz |
No of Units | 3 (Three) |
Excitation System | Brushless |
Efficiency | 96.0 % |
Type | Single Phase, Oil Immersed, Indoor |
Rated Capacity | 8.9 MVA |
Voltage Ratio | 132/11 KVA |
No of Units | 3 (Three) + 1 |
Vector Group | YNd11 |
Efficiency | 99.0 % |
Voltage Level | 132 kV |
Length | 25 km (approx.) |
Conductor Type | ACSR “Wolf” |
From | Powerhouse |
To | Tingla Substation, Solukhumbu |
Intake site | 10km from Sotang |
Powerhouse site | 3km from Phulpati Khola |
Construction period | 32 month |
IRR | 15.20 % |
EIRR/ROE | 22.79% |
Total Project Cost | NPR4,364,800,000 (With IDC) |
BC Ratio | 1.38 |